灯塔工程

项目需要

In 2012, the Eastern Treasure Valley Electrical Plan identified the need for the 灯塔工程. The plan forecasts electrical demand and reliability needs and addresses them through long-term planning. A community advisory committee (CAC) made up of business and government leaders played a key role in drafting the plan.

在廉政公署的支持下, 靠谱的电子游艺官网 is working to implement the plan, including planning and construction of a new Beacon Light Substation and transmission line.

The substation was built in 2020 at the corner of Beacon Light and Linder roads. 靠谱的电子游艺官网 obtained permits for it in 2006.

The city of Eagle approved the Beacon Light transmission route along State Highway 16 and Beacon Light Road in 2017. The city approved its design in 2018.

靠谱的电子游艺官网 completed construction in June 2020.

联系信息

If you have questions or comments about the 灯塔工程, contact:

项目经理 蒂姆•菲利普斯
208-388-2744
tphillips@greycomp.net

Facility Siting Coordinator Jeff Maffuccio
208-388-2402
jmaffuccio@greycomp.net

或将问题邮寄至:
靠谱的电子游艺官网
P.O. 70箱
博伊西,ID 83707